CASE STUDY

Heavy Machinery Relocation: 800MT
COMBINED TRANSPORT Challenge Across Asia

Untitled design.png

Project Details

From

:

Korea Factory

To

:

Chennai, India

Mode

:

Land + Sea + Land

Total Weight

:

4500 RT - Breakbulk

Cargo

:

2000 & 500ton Press

Frame.png

Our Challenge

The project involved relocating a 2,000-ton press machine and a 500-ton press machine from Korea to India. The scope required dismantling the machinery, packing, and transporting it with precision. The heaviest single piece, the 150-ton crown and accessories, posed unique challenges in handling, loading, and shipping. The operation demanded meticulous planning for heavy haulage, export documentation, and multimodal transport solutions.

Frame-2.png

Our Solution

  • Conducted a site survey in Korea to plan dismantling and transport 

  • Deployed an expert rigging team to dismantle the press machines in factory

  • Arranged heavy-haul transport to Masan port and shipped via breakbulk & container vessel to India 

  • Delivered all components on time and damage-free to the client in India

Frame-3.png

The Result

The project was completed successfully, with the 2,000-ton and 500-ton press machinery safely dismantled, packed, and shipped to India. The 100-ton crown was handled with precision, demonstrating Go Gauge's capability to manage complex heavy lift projects. The client appreciated the seamless execution, timely delivery, and our attention to detail in every phase of the project.